The contract involved the demolition of five bridge spans and reconstruction with pre-stressed concrete beams on new cills with in-situ concrete deck and new brick parapets.

Gallery (click on an image to view a larger version)

The works also involved the capping of a mine shaft, new brick faced reinforced concrete retaining wall and carriageway widening. The bridgeworks were constructed over Network Rail Property and involved working to the stringent requirements of Network Rail including a number of possessions.

Client Standish Street / Atlas Street Improvements
Contract St Helens MBC
Value £0.78m
Length 28 weeks